Tag: permit
Clear
  • NAO-2016-00134/VMRC#16-V0757

    Expiration date: 7/28/2016

    The applicant proposes to reduce bank erosion and eliminate sediment loading downstream within the Maury and James Rivers by restoring approximately 400 linear feet of the Maury River through the excavation of a mid-channel bar, discharging the excavated material and imported fill material along 450 feet of the left river bank to create a vegetated bankfull, floodplain bench; installing two rock vanes; sloping the riverbank and establishing a riparian buffer. The project is located in Glasgow, Virginia.

  • NAO-2015-01440

    Expiration date: 6/22/2016

    The sponsor proposes to establish, design, construct, and operate a compensatory wetland and stream mitigation site to be known as Thompson Place Bank. The purpose of the mitigation project is to provide off-site compensatory mitigation for projects that result in unavoidable impacts to wetlands and streams and other waters of the United States in the Upper New River Basin. The project is located near Blacksburg, Montgomery County, Virginia

  • NAO-2005-01473

    Expiration date: 7/16/2016

    The applicant proposes construct a portion of a sanitary sewer line associated with the development of an apartment complex consisting of 373 units and associated roads, utilities, and parking in Goochland County, Virginia. The project site drains into Broad Branch, a tributary to Tuckahoe Creek, which drains into the James River, a navigable water of the U.S.

  • NAO-2016-00961

    Expiration date: 7/8/2016

    The Navy proposes to continue the construction of the North Gate, South Gate and perimeter fence project that was originally authorized under a State Program General Permit (SPGP). The majority of the work has already been completed. The applicant proposes additional impacts, which are now beyond the limits of the SPGP. The total impacts for the project include fill in 0.22 acres of forested wetlands and permanent conversion of 1.10 acres of forested wetlands to emergent wetlands. The project is located at NASO Dam Neck Annex in Virginia Beach, Virginia in Redwing Lake and Lake Tecumseh, tributaries to Back Bay.

  • NAO-2014-00272

    Expiration date: 6/9/2016

    Fairfax – Department Public Works & Environmental Services proposes construction of the Huntington Levee and Pump Station Project. The purpose of the constructed levee and pumping station is to protect the homes and other property in the Huntington neighborhood from flooding. The project is located in Cameron Run and unnamed tributaries to Cameron Run in Huntington Park at the northern end of Liberty Drive in Fairfax County, Virginia.