Results:
Tag: James River
Clear
  • NAO-2019-1754

    Expiration date: 5/25/2020

    The applicant proposes to construct an expansion of the existing data center by constructing two additional single-story data center buildings, a two story administrative building, roads, stormwater management facilities, and associated utilities on a 292 acre parcel known as Project Echo Site 7.

  • WRD-PLNS=090420

    Expiration date: 5/11/2020

    The U.S. Army Corps of Engineers (USACE) Norfolk District and the City of Newport News are conducting a feasibility study authorized by Section 14 of the Flood Control Act of 1946 as amended for a shoreline stabilization project along the north bank of the James River in the City of Newport News.
  • NAO-2008-02069

    Expiration date: 12/21/2019

    The Corps of Engineers is amending the Navigation Regulations published at 33 C.F.R. §334.280, "James River, Skiffes Creek and Warwick River surrounding Joint Base Langley-Eustis, Virginia; restricted areas and danger zones."

  • NAO-2008-00254

    Expiration date: 9/16/2019

    The applicant proposes to discharge fill material in 2.56 acres of forested wetlands for the purpose of constructing an office building and attendant structures, including access roads and parking lots, to expand the existing on-site financial services call and data center.

  • NAO-2012-00080

    Expiration date: 9/3/2019

    On June 21, the Norfolk District Regulatory Branch issued a public notice soliciting comments as part of the scoping process for the preparation of an Environmental Impact Statement to evaluate project alternatives and public-interest review factors for the Virginia Electric Power Company (Dominion) proposal known as the “Surry-Skiffes Creek-Whealton Aerial Transmission Line Project.” In response to several requests, the comment period will be extended until Sept. 3.