Public Notice Distribution List

To be added to the Regulatory Branch Public Notice email distribution list, please send an email to Rod Desk at CENAO-.REG_ROD@usace.army.mil 

Results:
Tag: stream
Clear
  • NAO-2025-0692 (Route 750 Bridge Replacement)

    Expiration date: 5/19/2025

    VDOT will be replacing a bridge on Route 750 (Old Turnpike Rd) that crosses a tributary of Stockton Creek in Afton, VA. The existing bridge is a contributing feature of the historic district and the removal of the bridge is considered an adverse effect to the district. The bridge must be replaced due to safety concerns. In compliance with regulations implementing Section 106 of the National Historic Preservation Act (NHPA), the Corps is soliciting comments on the proposed project from the public; federal, state, and local agencies and officials; Native American Tribes; and other interested parties. Comments should be received by the close of business on May 19, 2025.

  • NAO-2013-02047-TREC (25-V0058) Myers Corner

    Expiration date: 5/13/2025

    Crescent Development requests authorization to construction Phase 5 and 6 of the residential development known as Myers Corner. Impacts to waters of the United States are associated with the construction of a stormwater management basin and a sanitary sewer connection. The Norfolk District will receive written comments on the proposed work until May 13, 2025.

  • NAO-2022-02394 / VMRC# 22-V2715 (Microsoft Data Center, Mecklenburg County, Virginia)

    Expiration date: 5/11/2023

    Microsoft proposes to construct a new data center facility to house servers used in cloud-based computing on a 369 acre parcel west of Skip with Road (SR 688) and north of Butler Farm Road (SR 831) in Mecklenburg County, Virginia.

  • NAO-2007-04662, Celestial Way Subdivision, Yorktown

    Expiration date: 9/12/2022

    The Lotz Family Limited Partnership seeks to construct a 43 lot single family home subdivision in Yorktown to meet a current housing demand in York County. The development will result in the loss of 1.86 acres of forested wetland and 102 linear feet of perennial stream across nine impacts areas on site for lot creation and associated infrastructure, as shown on the attached plans. The applicant plans to mitigate their impacts through the purchase of mitigation credits. Comments should be received by the close of business on September 12, 2022. 

  • NAO-2021-01244

    Expiration date: 2/27/2022

    The applicant proposes constructing a car dealership within a 7.22-acre project area, including parking spaces, a 40,000 square foot detention facility, and a 28,000 square foot building to be used as a show room, office space and repair facility, resulting in permanent impacts to 3.82 acres of forested wetlands and 3.4 acres of scrub shrub wetlands.