Results:
Tag: endangered species
Clear
  • NAO-2022-1382 MRC 22-1263(JSSY bulkhead and fill, Portsmouth, Virginia)

    Expiration date: 1/13/2023

    JSSY LLC is proposing the construction of a steel sheet-pile bulkhead and associated backfill at 3301 Shipwright Street in Portsmouth, Virginia, on the Western Branch of the Elizabeth River.

  • NAO-2018-01743

    Expiration date: 12/10/2022

    North Landing Beach RV Resort & Cottages-Virginia Beach, LLC proposes to remove gabion baskets, mechanically dredge and use the material for beach nourishment, construct piers, a bulkhead, a groin, and a timber walkway at 161 Princess Anne Road in Virginia Beach, Virginia. The applicant is also requesting after-the-fact authorization for previous impacts. The applicant is proposing to mitigate for the 2.28 acres of vegetated, nontidal wetland impacts through the purchase of 4.6 acres of mitigation bank credits. Comments on this project should be received by the close of business on December 12, 2022.

  • NAO-2014-00474 / VMRC# 22-V1758 (Microsoft Data Center, Clarksville Va.)

    Expiration date: 11/25/2022

    Microsoft proposes to construct a new data center facility to house servers used in cloud-based computing off Commerce Drive in Clarksville, Virginia and will result in the loss of 9.64 acres of wetlands and 1,703 linear feet of stream. Comments on this project should be received by the close of business on 24 November 2022.

  • NAO-1998-02442 (Botetourt Center at Greenfield)

    Expiration date: 4/9/2022

    Botetourt County proposes to widening an existing road within the Botetourt Center at Greenfield resulting in temporary and permanent impacts to an unnamed tributary of Tinker Creek. The perennial stream is located on the eastern side of Lots A, B, and C, and west of International Parkway. The impact area is located at approximately 37.438669 (latitude), -79.919651(longitude) and consists of 244 square feet of permanent stream impact across 105 linear feet of stream. Public comments should be received by April 9, 2022.

  • NAO-2021-01244

    Expiration date: 2/27/2022

    The applicant proposes constructing a car dealership within a 7.22-acre project area, including parking spaces, a 40,000 square foot detention facility, and a 28,000 square foot building to be used as a show room, office space and repair facility, resulting in permanent impacts to 3.82 acres of forested wetlands and 3.4 acres of scrub shrub wetlands.